Road Paving/Recycling Information and Schedule

0

The seven streets to be recycled and paved (Laurel, Roseland, Barkdale, Skyland, South Skyland, Waters, and Summer) are all being worked concurrently. See attached schedule which indicates that these seven roads are expected to be complete by August 31.

Macedonia Commons Boulevard will be performed at night. This work is scheduled to begin on Monday night (07-31-17) with asphalt milling. The paving at Commons is scheduled to be complete by the end of Thursday night. Striping and traffic signal trips to immediately follow.

Sioux Lane paving will follow the replacement of the culvert.

All other items (spot asphalt repairs, catch basin repairs, crack sealing, etc…) will occur after September 01